Getting to Know 1500 kVA Generators
A 1500 kVA (1.5 MVA) generator is about 1200 kW at a power factor of 0.8. This large class serves data centres, heavy industry, mining and large hospitals.
A silent container option is available for outdoor installation. Where one unit is not enough, several generators can be synchronized in parallel.
Suited to
- Data centres
- Heavy industry
- Mining
- Large hospitals
- High-rise buildings
Prime or Standby?
Main power
1500 kVA prime
- The generator is the main power source, for example at a site without grid power
- It runs long hours every day with a varying load
e.g. BJPS-1500-WP
Grid backup
1500 kVA standby
- The generator only runs during grid outages
- Prime slightly below 1500 kVA, standby around 1500 kVA: usually more economical
e.g. CJPS C-1375 WP
1500 kVA Generator Options
Every JERBINDO 1500 kVA model by engine brand. Select a model for full specifications.
Mitsubishi engine
Fuel at 75% (prime): 237–250 L/hr3 models
| Model | Prime kVA | Standby kVA |
|---|---|---|
| MJPS-1500-CS12R-PTAA2-C1500 kVA prime | 1500 | 1650 |
| MJPS-1500-C-leroyS12R-PTAA2-C1500 kVA prime | 1500 | 1650 |
| MJPS-1500-SizeS12R-PTAA21500 kVA prime | 1500 | 1650 |
Cummins engine
Fuel at 75% (prime): 238 L/hr2 models
| Model | Prime kVA | Standby kVA |
|---|---|---|
| CJPS C-1500 WPKTA50-GS81500 kVA prime | 1500 | 1650 |
| CJPS C-1375 WPKTA50-G81500 kVA standby | 1375 | 1512.5 |
Baudouin engine
1 models
| Model | Prime kVA | Standby kVA |
|---|---|---|
| BJPS-1500-WP12M33G1650/51500 kVA prime | 1500 | 1650 |
Perkins engine
Fuel at 75% (prime): 237 L/hr1 models
| Model | Prime kVA | Standby kVA |
|---|---|---|
| PJPS-1500 WP14012-46TAG2A1500 kVA prime | 1500 | 1650 |
Generator Room Requirements
General guidance for the 1500 kVA class from engine and generator makers' installation manuals. Final figures follow the installation drawings and datasheet of the chosen unit.
- Minimum room, 1 unit
- 8.7 × 5.3 m
- Open type (L × W × H)
- 4800–5700 × 2150–2270 × 2430–2700 mm
- Silent canopy (L × W × H)
- 7700–12192 × 2438–2800 × 2896–3150 mm
Service clearance
1.5 m per side
- Leave at least about 1.5 m of clear space on every side of the generator for maintenance (Cummins' guide for units from 100 kVA; other sources give 0.9–1.2 m), plus room above it to open panels. With the largest open unit in this class, one generator needs a room of at least about 8.7 × 5.3 m.
- When installing more than one unit, leave about 2 m between generators.
- Also keep a route and door wide enough to bring the unit in and to remove large parts such as the radiator or alternator.
Ventilation
Outlet ≈ 1.5× radiator
- Provide an air inlet behind the generator and an outlet in front of the radiator. As a general guide, the outlet is about 1.5× the radiator core area and the inlet 1.5–2× (louvres cut the free area by about 25%). Keep the room no more than about 7–10 °C above outdoor air; above 40 °C the generator needs derating.
- Radiator airflow in this class is very large, so a radiator duct to the outside or a silent container outside the building is usually needed.
Foundation
≥ 2× unit weight
- A concrete foundation of at least about 2× the generator's weight, extending 150–300 mm beyond the skid on every side, with vibration isolators between the skid and the foundation. Let the concrete cure for 28 days before loading. Dry weight of the open units in this class: 8.6–14 tonnes.
- At this weight, the foundation and floor structure should be designed by a structural engineer.
Day tank
1900–2000 L / 8 hours
- Fuel use at 75% load: 237–250 L/hr, or about 1900–2000 L for 8 hours of running. Size the day tank from this; for longer running add a bulk tank with a transfer pump.
- NFPA 37 limits a tank inside the generator room to 2,500 L unless it has its own fire-rated room; local regulations also apply.
Exhaust
Backpressure ≤ datasheet
- A flexible connector at the engine outlet; pipework supported on its own so it does not load the engine, insulated and fitted with a rain cap. Choose the pipe and silencer so backpressure stays within the engine datasheet limit; avoid long runs and many bends. Discharge away from the air inlet.
- Large units usually use residential or critical grade silencers, with a separate exhaust run per unit when running in parallel.
Configuration
Open · Silent · Container
- Open units for a generator room; silent canopy or silent container for outdoors.
- A synchronizing panel for parallel operation of several units, including load sharing and N+1 redundancy.
Generator Projects Around 1500 kVA
Projects from our project list with units of around 1500 kVA.

Power & Utilities
Perkins 2 x 1500 & 1000 kVA Silent Type
North Barito, Central Kalimantan

Office & Commercial Buildings
Perkins 2 x 1500 & 1000 kVA Open Type
Tanah Bumbu, South Kalimantan
More project references, 2021–2026
5 projects with units of around 1500 kVA in our 2021–2026 project list. Client names are not shown.
Baudouin 1500 kVA
Hospital
Malang, East Java · 2026
Baudouin 1500 kVA
Water supply & pumping station
Makassar, South Sulawesi · 2024
Mitsubishi 1500 kVA
Data center & telecom
Surabaya, East Java · 2022
Cummins 1500 kVA
Hospital
Bojonegoro, East Java · 2025
Perkins 1500 kVA
Hospital
Surabaya, East Java · 2023
Frequently Asked Questions
How much does a 1500 kVA generator cost?
The price of a 1500 kVA generator depends on the engine brand, the configuration (open type, silent canopy, silent container), an ATS/AMF or synchronizing panel, installation and commissioning, the delivery location, and the warranty and after-sales service. Use Request a Quote with your requirements and our sales team will send a quotation. What shapes a generator price
How many kW is a 1500 kVA generator?
At the 0.8 power factor commonly used for generators, 1500 kVA equals 1200 kW. The exact kW of each model is on its specification page.
How much diesel does a 1500 kVA generator use?
At 75% load, the 1500 kVA prime generators in our catalogue use about 237–250 L/hr, depending on the engine brand and model. Fuel use at 50% and 100% load is on each model's page.
Should I choose 1500 kVA prime or standby?
Choose a 1500 kVA prime model if the generator is the main power source or runs long hours with a varying load. If you need 1500 kVA only as backup during grid outages, a model with a 1500 kVA standby rating (and a slightly lower prime rating) is usually enough and more economical.

Trusted by Various Companies
Decades of experience and a portfolio of projects across many sectors reflect our commitment to quality.
Our clients
Explore More Generator Solutions

Find the Right Industrial Generator Solution
Discuss your power requirements with our sales and service team to get the right products and services.